Construction Update- Noisy Work in and Around 2200 Building

Hello Campus Community,

Starting Tuesday, 6/27, through Tuesday, July 18th, Forma will be conducting noisy work in and around the 2200 building.  They will be performing HVAC work in the roof from June 27th to July 9th

On July 10th, a mobile crane will be onsite to lift the new HVAC unit from the South side of #2200 to the roof. After that they are installing a new gas line on the East exterior wall the week of July 18th.  The most disruptive part of this work will be the crane work. 

Please reach out to Kim Clark (kclark@shoreline.edu) with any questions or concerns.