Hello Campus Community,
We are getting close to starting our STEAM (Bracken) building project. Bayley, our contractor, has provided a schedule for the next few months. A few tasks to highlight will be the construction of a new ramp from 2300, Abatement of 2200, Demoing of 2200, and tree removal around the new STEAM site.
Each of these tasks will result in noisy work and dust. Below is the fence plan which highlights where they will place their construction fencing around campus. As part of the fencing, Bayley will be constructing a new ramp on the west side of 1800 for access to 1800 building from the west parking lots.


More information to follow as the project team and Bayley start our weekly construction meetings, and more information is provided.
Feel free to reach out if you have any questions.
Activities Scheduled For Next 6wks (5/20/2024 – 6/28/2024)
Prepping area and investigating 2200 building = May 28th-June 7th
Bayley Trailer placed on campus = May 29th
Bayley construct ramp to building 2300 = June 3rd-June 5th
Fence install = June 6th-June 7th (after egress is complete)
Dixon perform abatement and demo of building 2200 = Abatement June 10th-June 16th. Demo of 2200 June 17th – July 5th
Tree Removal – Arborist onsite = Start June 10th
Thank you.
Kimberlee Clark
Director of Facilities and Capital Projects