Hello Campus Community,
We are set to start the roof project for the campus next week. This project consists of repairs to building 1000, 2900, 3000, 4000 and 1600. The schedule is as follows.
- 2/10/25 – 2/17/25
- 1000 Building Cupolas – Contractor will be removing and replacing cupolas on roof. There will be minimal noise and vibration. No impact to the art in the art gallery. There is a chance of a slight chemical smell when they install the new Cupolas. SDS is attached.
- 2/18/25 – 2/28/25
- 2900 roof gravel replacement and perimeter work – Contractor will remove roof gravel, repair roof, and replace gravel. There will be a slight vibration over walkways with little to no impact within the building. There will be slight noise and chemical smell. Parking on the east side of building (close to wall) will be taken offline while gravel is removed. SDS is attached.
- 3/3/25 – 3/14/25
- 3000 soffit stain work – Contractor will be using a lift and scaffold to apply a stain to the soffit around the building. They will start on the east side of 3000. No vehicles can be parked in the parking stalls on the east side of 3000 when they start to apply the stain. It will take them 1-2 days to complete the work on the NE side of 3000. SDS is attached.
- 3/17/25 – 3/28/25
- 4000 skylight replacement – Contractor will remove existing skylight and replace with new. There will be noise and chemical smells during this project. To minimize the impact of dust/sawdust falling within the library, a section inside the 2nd floor will be closed off during the project. SDS is attached.
- 3/31/25 – 4/4/25
- 1600 PMMA and drain replacement – Contractor will be replacing the roof drainage system. This will require interior and exterior work. There will be slight noise and chemical smell. SDS is attached.
The contractor will do their best to minimize noise during this roof project. Facilities will do our best to minimize any impact to the buildings while chemicals are being used. This schedule could change slightly since much of this work is weather dependent. We’ll be working with building occupants if any changes occur. Feel free to reach out if you have any questions.
Thank you for your patience while we complete this project.