Campus Power Shut Down, Round 2

Bayley will be shutting down power to the following buildings as part of the ongoing work for the Bracken building.  The following buildings will be shut down on Saturday, 11/1, starting at 2:30pm through Sunday, 11/2, until 7pm:

  • 1800
  • 1900
  • 2000
  • 2100
  • 2300

No electrical or heat will be available during these dates/times.  Please reach out to the office of Facilities & Capital Projects if you have any questions.

Water Leak in the 9000 Building – 7//24/2025

We had some flooding in 9000 this evening that impacted 9101 Ebbtide, 9201 Multicultural Center, and the 1st floor south entryway.

Custodial and maintenance have cleaned up the water and are currently drying out the spaces.  These areas will be closed while drying.

The cause of the leak has been identified and resolved.

Feel free to reach out to Facilities if you have any questions.

Facilities Updates- Roof and Bridge Work

Hello Campus Community,

Update 1: Roof Work

Our recent roof project got off track due to the ice and the need to do more repairs to the roof at 2900 building.  Due to these delays, the 2900 building is still in process and the timeline for 3000, 4000, and 1600 has shifted.  Here is the new schedule starting next week. 

  • 3/21/25
    • 2900 roof gravel replacement and perimeter work will be completed by Friday, 3/21.  Contractor will be removing their equipment from that area.  Parking in front of that building will be open starting Monday, 3/24.
  • 3/24/25 – 4/1/25
    • 3000 soffit stain work – Contractor will be using a lift and scaffold to apply a stain to the soffit around the building.  They will start spraying on the south side starting Tuesday, 3/25.  No vehicles can be parked in the motorcycle parking stalls on the north side and the parking stalls on the east side of 3000 when they start to apply the stain.  Security will close off the parking in these areas starting Tuesday.  Parking should be back open on Monday, 3/31. 
  • 3/24/25 – 4/4/25
    • 4000 skylight replacement – Contractor will remove existing skylight and replace with new.  There will be noise and chemical smells during this project.  To minimize the impact of dust/sawdust falling within the library, a section inside the 2nd floor will be closed starting Monday, 3/24.   
  • 4/1/25/25 – 4/8/25
    • 1600 PMMA and drain replacement – Contractor will be replacing the roof drainage system.  This will require interior and exterior work.  There will be slight noise and chemical smell. 

Feel free to reach out if you have any questions. Please check your e-mail for the SDS forms.

Update 2: Bridge Repair

We will be starting our pedestrian bridge repair project at building 3000 next week.  The purpose of this project is to reseal the top deck of the pedestrian bridge, resurface and fill in the cracks on the pedestrian ramp, and repair/seal the concrete underneath the pedestrian bridge.  The project schedule will run from 3/24/25 to 6/5/25.   

3/24/25-4/4/25 – Contractor will start with the top of pedestrian bridge.  The bridge will be closed in sections to allow for access.  The Contractor will also be closing the ramp at 3000 to resurface and fill in the cracks.  SDS for the sealant will soon follow. 

4/21/25 – 5/16/25 – Contractor will be working underneath the 3000 pedestrian bridge to seal/repair the concrete.  There will be access to 3000 underneath the bridge.

Feel free to reach out if you have any questions.

Thank you,

Kim Clark

Director of Facilities and Capital Projects

Construction Work in Building 1600

Hello Campus Community,

The college has been approved for an emergency declaration to mitigate flooding issue in the orchestra pit in 1600.  Work began yesterday 12/18/24. The stage apron will be dissembled to remove the orchestra pit floor.  The stage apron will then be re-installed to ensure the stage can continue to be used while we mitigate the flooding issue.  There will be no impact to building 1600 and any scheduled productions will be able to proceed.  The contractor will work to resolve the issue with the orchestra pit flooding when the stage is not in use.  This project should be completed by the end of January 2025.  Feel free to reach out if you have any questions. 

Thank you,    

Kimberlee Clark

Director of Facilities and Capital Projects

Construction Update: Bracken Fence Line Changing

Hello Campus Community,

Bayley Construction will be temporarily moving the fence line for the Bracken project to accommodate the crane.  The accessibility path to 6000 will be shifted to the ramp and walk path on the west side of 2900. The map below outlines the new fence line and accessibility path.   Please reach out if there are any questions.   

Thank you for your patience during construction.  

Kimberlee Clark, Director of Facilities and Capital Projects

This is a picture of the construction zone showing the new location of the fence line.