HSAMCC – August 2022

Week 7/4/22 through Week of 8/29/22 – Progress Updates

  • During July and August, construction work and activities included the following:
    • Major structural steel members were installed up through Level 3 and the
    roof which completed the main structure. A topping out party was held to commemorate the last steel member installation. The steel metal decks that support the floors were installed on Level 2 and Level 3. This included pouring of the concrete for these floors as well. Steel prefabricated stairwells on the East and West ends began welding activities for attaching to the main structure. Interior mechanical, electrical, plumbing, and fire protection supports that hold the utilities in the ceilings were installed on each concrete floor. The exterior metal stud framing began on Level 1. Fireproofing prep work that protects the steel members began on the interior of Level 1. Site electrical underground work on the East side of campus and towards the PUB continued North up to the project. Road closures for this work continued. Andrea Wilbur-Sigo, the project-selected artist plans to present ideas to the art committee this Fall. The location for the art has yet to be determined. Interior signage and donor sign design progress continue to evolve. Furniture design and selection of products also continue to make progress.
    • Next few months the project will continue to work on finishing up metal framing and beginning the exterior sheathing. The next big milestones for the months ahead include:
      • Roof structure completion.
      • Exterior finishes.
      • Dry-In of floors L1, L2, and L3. This will kick off interior scopes of work.
  • The critical path and the completion date tracking for a Summer/Fall 2023 building completion.
  • Notices regarding road closures, loud work, shutdowns, or interruptions continue to be shared with the Faculty and Staff, and the College’s campus neighbors.
HSAMCC Construction Project progress pictures
HSAMCC Construction Project progress pictures
HSAMCC Construction Project progress pictures
HSAMCC Construction Project progress pictures
HSAMCC Construction Project progress pictures
HSAMCC Construction Project progress pictures
HSAMCC Construction Project progress pictures

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: