HSAMCC Construction Update 12/2/22

(SCC HSAMCC). You can play and download from here.

Project Details – Heath Science Advanced Manufacturing Classroom Complex

  • The HSAMCC will replace five previously existing buildings (2400, 2500, 2600, 2700, and 2800) with the construction of a new 50,700 square foot multi-instructional facility.
  • The building is located on the footprint of the previously existing 2500 Building.
  • The HSAMCC provides state-of-the-art educational spaces for Chemistry, Biology, Medical Lab Technology, Engineering, Advanced Manufacturing and Bio-Manufacturing.
  • When finished in August of 2023, the three-story structure will have a south-facing territorial view of natural spaces that preserve existing, significant trees and landscape features.
  • The complex will integrate enhanced outdoor student and community gathering areas.

High Level Construction Summary Timeline

Summer 2021:   Contractor mobilization and construction start – Complete

Summer 2021:   Demolition Phase I included existing buildings 2500 and North 2400 buildings including greenhouse and infiltration pond – Complete

Summer 2022:   Greenwood parking lot infiltration pond construction – Complete

Summer/Fall 2023:   Building occupancy compliance/completion and college teams move-in to HSAMCC.

Fall/Winter 2023:  Demolition Phase II includes existing buildings 2600, 2700, and 2800, and South 2400 buildings.

Winter/Spring 2024:  Landscaping of new courtyard and overall project completion (includes new greenhouse and pond). This will coincide with the future STE(A)M project development.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

%d bloggers like this: