Project Details – Heath Science Advanced Manufacturing Classroom Complex
- The HSAMCC will replace five previously existing buildings (2400, 2500, 2600, 2700, and 2800) with the construction of a new 50,700 square foot multi-instructional facility.
- The building is located on the footprint of the previously existing 2500 Building.
- The HSAMCC provides state-of-the-art educational spaces for Chemistry, Biology, Medical Lab Technology, Engineering, Advanced Manufacturing and Bio-Manufacturing.
- When finished in August of 2023, the three-story structure will have a south-facing territorial view of natural spaces that preserve existing, significant trees and landscape features.
- The complex will integrate enhanced outdoor student and community gathering areas.
High Level Construction Summary Timeline
Summer 2021: Contractor mobilization and construction start – Complete
Summer 2021: Demolition Phase I included existing buildings 2500 and North 2400 buildings including greenhouse and infiltration pond – Complete
Summer 2022: Greenwood parking lot infiltration pond construction – Complete
Summer/Fall 2023: Building occupancy compliance/completion and college teams move-in to HSAMCC.
Fall/Winter 2023: Demolition Phase II includes existing buildings 2600, 2700, and 2800, and South 2400 buildings.
Winter/Spring 2024: Landscaping of new courtyard and overall project completion (includes new greenhouse and pond). This will coincide with the future STE(A)M project development.