Buildings 800 and 2300 have been officially handed over to Bayley for phase 2 of the Bracken project. Preparation for demolition has begun according to the following schedule:
Building 2300
- 4/22 – 4/27: Abatement
- 4/27 – 5/12: Full Demolition
Building 800
- 4/24 – 4/28: Abatement
- 4/29 – 5/14: Full Demolition
In preparation for the demolition of Building 2300, Wartel will temporarily shut off power to Buildings 2000 and 2100 this Thursday, 4/23, from 5am – 6:30am. This outage is necessary to safely disconnect Building 2300 in preparation for its scheduled demolition.
We appreciate your patience during this necessary prep work. Feel free to reach out to Facilities if there are any questions.