Opening Week- Coffee with the President!

Take a look at Opening Week, Coffee with President Jack Kahn!

Coffee with the President photo
Coffee with the President photo

Coffee with the President photo
Coffee with the President photo

Executive Director Position Announcement

Hello!

Shoreline Community College is recruiting for an exciting new position:

            Admin/Exempt- Executive Director – Institutional Effectiveness

 Opened: 9/22/22

 Date of first consideration: 10/13/22

https://www.schooljobs.com/careers/shorelinecc/jobs/3735329/admin-exempt-executive-director-institutional-effectiveness

Interested applicants may apply using the link listed above or go to www.shoreline.edu/hr for this and all our full-time and part-time positions available. 

Please share with your colleagues and professional networks!

Update: Roof Repair Report

Dear Campus Community, 

We are gearing up for day two of Opening Week and are looking forward to seeing folks around campus! This is a follow-up email to yesterday’s roof repair email.  

As promised, the full report from PBS Engineering and Environmental, Inc. (this is the company that conducted the Volatile Organic Compound (VOC) testing) can be accessed here.  The results of the onsite inspection indicated that, based on the Volatile Organic Compound (VOC) readings in and around the building, the odor created by the adhesive is non-toxic.   

If you are experiencing a reaction to the odor, we are more than happy to explore alternative work options, including relocating to a different facility to ensure conducive and comfortable working conditions. Please reach out to HR to make a request.  

In addition to the odor, we understand that noise from the roof repair may become distracting and hard to work nearby. Please reach out to HR to request an alternative work area.  

If you have additional questions or concerns about this, we encourage you to reach out to the Facilities Department.  

Facilities Contact: 

Bob Williamson 

Acting Vice President for Business and Administrative Services 

rwilliamson@shoreline.edu 

Just a few more days and campus will be full of students making decisions to better their lives, and we get to be a part of that! 

Thank you for all that you do for our campus and students! 

HSAMCC – August 2022

Week 7/4/22 through Week of 8/29/22 – Progress Updates

  • During July and August, construction work and activities included the following:
    • Major structural steel members were installed up through Level 3 and the
    roof which completed the main structure. A topping out party was held to commemorate the last steel member installation. The steel metal decks that support the floors were installed on Level 2 and Level 3. This included pouring of the concrete for these floors as well. Steel prefabricated stairwells on the East and West ends began welding activities for attaching to the main structure. Interior mechanical, electrical, plumbing, and fire protection supports that hold the utilities in the ceilings were installed on each concrete floor. The exterior metal stud framing began on Level 1. Fireproofing prep work that protects the steel members began on the interior of Level 1. Site electrical underground work on the East side of campus and towards the PUB continued North up to the project. Road closures for this work continued. Andrea Wilbur-Sigo, the project-selected artist plans to present ideas to the art committee this Fall. The location for the art has yet to be determined. Interior signage and donor sign design progress continue to evolve. Furniture design and selection of products also continue to make progress.
    • Next few months the project will continue to work on finishing up metal framing and beginning the exterior sheathing. The next big milestones for the months ahead include:
      • Roof structure completion.
      • Exterior finishes.
      • Dry-In of floors L1, L2, and L3. This will kick off interior scopes of work.
  • The critical path and the completion date tracking for a Summer/Fall 2023 building completion.
  • Notices regarding road closures, loud work, shutdowns, or interruptions continue to be shared with the Faculty and Staff, and the College’s campus neighbors.
HSAMCC Construction Project progress pictures
HSAMCC Construction Project progress pictures
HSAMCC Construction Project progress pictures
HSAMCC Construction Project progress pictures
HSAMCC Construction Project progress pictures
HSAMCC Construction Project progress pictures
HSAMCC Construction Project progress pictures

Grand Re-Opening of the Veterans Resource Center (VRC)

Please join us for the Grand Re-Opening of the Veterans Resource Center (VRC) – FOSS 5226 – Monday, October 3rd – Thursday, October 6th.

The introduction of Jim Armstrong!  Veteran & Military Student Services (VMSS) received an Innovation Grant this year and were lucky to hire Jim as our new Program Specialist II.

Jim is responsible for managing our Veterans Resource Center (VRC) and will focus on the student experience,  increasing on-campus student support, outreach, and retention.  Jim brings passion and immense experience to our team and we are thrilled to have him on board.

AND…If you haven’t yet met Morgan Davis, Shoreline’s fantastic on-campus Vet Corps Navigator, this is your opportunity!  Morgan is in her second year as Shoreline’s Navigator and is an integral part of student success.  Morgan will work with directly with Jim to provide increased student support, including access to off-campus resources and services.

It has been a while since we have all been together and there are so many new faces on campus, so we hope you will stop by for coffee, food, laughter, and connection!