Message from Facilities Director J. Francois: Update 1 – Right of Way (ROW) Improvements

Dear Colleague,

The team working on the Right of Way (ROW) improvements along NW Innis Arden Way discovered a conflict between the intended storm drain path and a utility run. While this issue is in review, the team intends to move forward with phase 2, highlighted in yellow on this ROW improvement phasing map.

Starting today (Monday, April 22nd), work at this corner of the intersection will commence. This portion is expected to take between two and three weeks.

The current plan is to then move to subsequent phases. We will return to phase 1 when possible. I will send additional updates as work progresses.

Please contact me if you have any questions.

Sincerely,
Jason Francois
Director-Facilities and Capital Projects

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s