West Gate Closure

College community –

Starting Monday, May 23, through Thursday, May 26, the West Gate will be closed for access due to re-paving.  We apologize for the short notice and inconvenience.  This work was quickly scheduled to align with the sunny weather we are expected to have this week. 

Thank you.   

Bob Williamson

Excavating around the 2300 and 2600 buildings this week 4/4-4/8

Hello Everyone,

The contractor will be excavating around the 2300 and 2600 buildings next week (4/4 – 4/8).  We anticipate increased vibration and noise around these buildings while the contractor performs the work.  Please reach out if you have any questions or concerns.

Thank you for your patience, 

Kimberlee Clark

Director of Facilities and Capital Projects

HSMACC building will require another shutdown 3/28-3/30/22

College community,

 Ongoing construction of the new HSMACC building will require another shutdown.  Gas will be shut off in the 2000, 2100, 2300, 2400 Boiler, and 2600 buildings from 8:00 a.m. on March 28 through 3:00 p.m. on March 30.  Buildings 2220 and 2700 will lose heat during this time as well.   The PUB and student housing will not be impacted.

We scheduled this work for spring break to minimize disruption and inconvenience for faculty, staff, and students.

Let me know if you have any questions.

Thank you.

 Bob Williamson

Acting Vice President for Business and Administrative Services

HSAMCC- Progress Updates

  • The first concrete pour for the project for the structural footings began on 12/1/21. Concrete foundation work was moving as scheduled prior to Local 174 Teamsters going on strike effecting our ability to get concrete. The strike is still ongoing, and the project completion date has been pushed back a few weeks due to these impacts to our critical path. Further, the snow fall after Christmas stalled progress in the month of December as well. The team continues to make do by performing other work that isn’t associated with concrete.
  • New underground storm and plumbing piping within the building footprint started and is making progress and got about 30% complete in these areas. Major sections of pipe that have been tested and inspected have begun the process of being backfilled.
  • Notices continue to be shared with the College’s campus neighbors on changing site conditions and traffic updates.
hsamcc building updates
hsamcc building update
hsamcc building update

SCC-HSAMCC 2018-102: Sewer Shutdown 12/22/21 to 12/23/21

There will be a sewer shutdown on Dec. 22 – 23, 2021.  

Time Frame:

Wednesday 12-22-21 7:00 AM to Thursday 12-23-21 3:00 PM, 2 Days

Areas Impacted:

Toilets, urinals, and sink drains in buildings #2300, #2200, and #1900

Description:

We will be tying the new sewer main to the existing system within our site fence line, adjacent to building #2300. This work will be outside of the buildings. We need to cut the sewer line that leaves #2300 and tie in the new line. We will also be installing a new structure that will intercept the sewer line that serves #2200 and #1900. We are requesting that the college does not use toilets, urinals or sinks in these buildings during the shutdown duration. No support will be needed from the college for this work. FORMA can provide and set up “Bathroom Closed” signage if needed. This work also includes the scope in RFI #048.