Important System Outage Update 5/12/23

Good afternoon,

Yesterday we shared some important ransomware updates in our campus forum that we also want to share with you here, in case you were unable to attend. 

Positive Progress 

We have made some really great progress with our recovery and restoration efforts. A huge thank you to TSS for their dedication and round-the-clock work during this time. 

  • Campuswide wireless has been restored. TSS has mounted 100 access points, which took approximately three weeks. Most every working area has full coverage; however, we are aware of a few outstanding areas. We are putting in an order for 20 additional access points to resolve those issues. 
  • Sixty-two new teaching computers were installed in classrooms for spring courses. These computers connect to Wi-Fi. TSS is currently working to ensure that all summer and fall classrooms will be ready and anticipate having the wired network restored for all classrooms and instructional areas that will be in use by Fall quarter.
    • The College has worked to get the student classroom labs operational for Spring quarter and that restoration effort is 97% complete. 
  • 55 laptops have been deployed by TSS and 250 desktops have been ordered and will be deployed during the Summer quarter. 
  • TSS is currently working on implementing several improved security protocols across the entire Shoreline infrastructure, which we will provide additional updates on. 
  • We now have a temporary solution for our intranet and are working to repopulate the documents and information. 

Important Data Restoration Update 

We have been working with the Dell EMC team for the past six weeks to reestablish the connection to the back-up data in the cloud. Unfortunately, we were made aware that despite their best efforts, Dell was unable to recover the data stored in the cloud. Data stored locally on desktop computers can be unencrypted and returned to the user. We have consulted other engineers for a second opinion, and unfortunately, they have also concluded the same as Dell. 

As a result, we will need to recover data in other ways and rebuild. Here are some steps we are currently taking: 

  • Data Identification
    • We have created a data identification spreadsheet to help us navigate the platform and service needs for every department across campus. This spreadsheet was shared with ET this morning. Meetings are being set up with department heads across campus to work with their teams and populate the document for review.
      • Once we receive the information back from the departments, we will have a clearer picture of the data and rebuild needs for the campus 
  • File Restoration Efforts
    • TSS has begun working through the submitted requests for local desktop file restoration, and thus far efforts have proven successful. To be added to the queue for local file restoration, please submit a ticket via this form. 

On Monday we will be sharing out some other helpful information about website requests and OneDrive/SharePoint, so stay tuned for more updates. 

We thank you for your continued patience and flexibility as we truly appreciate your efforts. Thank you for being a wonderful campus community. 

Cat 

Construction Update for 3000 Building and 2900 Parking Lot

Hello Campus Community,

We have a minor improvement project starting this week.  This is an accessibility project for the 3000 building and 2900 parking lot.  For this project, the contractor will be installing a ramp on the north side of the 3000 building to allow for accessibility access to the 1st floor of the 3000 building.  The contractor will also be adjusting the slope for 2 accessibility parking stalls on the south side of the 2900 building parking lot.  This project has been divided into two phases.  The first phase will be the ramp which will generate noise on campus while they break up concrete.  The NE stairwell for 3000 will have intermittent accessibility as they break up the concrete and replace.  There will be access on the NW side of 3000 and access to the motorcycle parking on the north side of 3000.  The second phase will include repaving the 2 accessibility stalls on south side of 2900.  The purpose is to adjust the slope of the parking stalls and to provide a correctly sloped path from the parking stalls to the new ramp.  There will be intermittent impacts to the 2900 parking lot.  More communication will be sent once I receive the schedule and impacts to the 3000 and 2900.  

Feel free to contact me if you have any questions.  

Thank you,

Kim Clark  

This is a diagram of the project location and area of impact described in the e-mail.

Today (5/11)- Fire Alarm Strobe and Horn Test, Bldg. 1600

Campus Community,

Last night, the college was made aware of a mandatory compliance test that is going to take place today, May 11th in Building 1600. Today from 2:00PM-3:30PM, the Bldg. 1600 fire alarm will be activated for short periods as the Fire Marshal’s Office conducts a final review of our new Bldg. 1600 fire system. Unfortunately, the timing of this test cannot be changed. I apologize for the distraction that this will cause the programs surrounding Bldg. 1600. If you have any questions, please feel free to contact me at gcranson@shoreline.edu

Respectfully,

Gregory Cranson

Director of Safety & Security

UPDATED- IMPORTANT: No Running water today (5/8/23) in 2600, 2700, 2800 & 2900

UPDATE: 1:38pm The water has been restored and bathrooms have been opened.

Attention Campus Community,

We’ve been notified that a water line has been cut due to construction for HSAMCC.  The contractor, Forma, is working to locate parts and fix the water line today.  The following buildings have been impacted, 2600, 2700, 2800, and 2900.  These buildings have no access to running water at the sinks or bathrooms.  Maintenance is working to put up signage at the bathrooms to direct people to other locations.  Please reach out to Kim Clark (kclark@shoreline.edu) if you have any questions. 

Thank you,

Kim Clark 

Parking Permit Update

Dear Campus Community,

Just a reminder, parking permit enforcement begins on Monday, May 1st. Vehicles without a parking permit from 6:00am-4:00pm, Monday-Friday, will be subject to citation. Student vehicles parked in Staff Lots will be subject to citation. Vehicles parked in designated zones (Parent Child Center, Campus Facilities, Campus Security) will be subject to citation. And as always, ADA violations, Fire Lane violations, illegal parking, hazardous illegal parking, and students/staff parking in the Visitor Lot will all be subject to citations. 

Daily permits can be purchased at the machines located around campus. Student quarterly permits can be purchased at Cashiering on the 2nd Floor of Bldg. 5000 (FOSS). And staff/faculty should follow the guidance posted HERE

Office Hours: 

8am-4pm (Monday-Friday) 

8am-4pm (Friday) 

Respectfully, 

Gregory Cranson

Director │ Department of Safety & Security